Hengtong deliveried the first wind turbine installation

2019-04-16 16:30:57

 

In the afternoon of April 9 (Beijing Time), the "Huadian Wenqiang" wind power operation platform, invested and built by Hengtong, has successfully deliveredits first wind turbine installation, demonstrating Hengtong's comprehensive strength.
 
微信图片_20190416163309.png
 
Compared with terristrial, the wind&wave, geology and meteorological condition greatly increase the difficulty of wind power equipment installation which is a major bottleneck restricting the development of offshore wind power.
 
On March 11, 2019, "Huadian Wenqiang" platform set sail to Zhanjiang,Guangdong Province to carry out the offshore wind power project in which first large-scale used large-diameter single pile in Guangdong Province. The construction site of the project is located in the high incidence area of typhoon. Complex geological sea condition, extreme working environment, limited construction surface and the dense cross operation, all of these increase the construction difficulty for the project team.
 
Considering the operation environment, Hengtong studied the working condition, and continuously optimized the construction scheme. Then developed facilities including single-blade hangers, tooling to improve the efficiency and safety of offshore fan hoisting, effectively ensure the installation accuracy and construction progress, and successfully complete the first fan installation.
 
The success installing the first wind turbine reflects the professional construction of the Hengtong wind power operation platform under complex sea conditions, and the comprehensive competitive strength of Hengtong in the field of offshore wind power, which will help Hengtong accumulate practical experience inbuilding offshore wind power and offshore engineering industry chain.
 
Offshore wind power construction platform, also known as "offshore wind power installation vessel", is used to carry out offshore wind turbine, basic transportation and installation construction. With four pilelegs, the platform is firmly and stalely inserted into the sea floor and . It is a necessary tool for offshore wind power installation to carry out construction successfully.
 
微信图片_20190416163313.png
 
"Huadian Wenqiang" platformwas constructed in January 2018 and  completed on February 15, 2019. The platform, a four pile leg non-autonomous but self-propelled wind power platform, covers the demand of wind farms in coastal areas and shallow sea areas in China. It has the advantages of high efficiency, energy saving, reasonable design, advanced configuration and economic cost.


    
 
Recommended information
CommunicAsia 2024
CommunicAsia 2024
OFC 2024: Optical Fiber Communications Conference and Exhibition
OFC 2024: Optical Fi
YOFC Hosts ICT Summit for Chinese Enterprises in Peru
YOFC Hosts ICT Summi
Following the Paths of Light for Over Five Decades | FiberHome Releases the New Smart Optical Network LIGHTS UP Solution
Following the Paths